The world of koi and garden ponds

The pool of Serge — Preparation and pickets

Construction with ECOLAT and ECOPIC · Part 1

This report shows how to prepare the edges of a pond with ECOLAT strips and pickets. The edges exist in the heights of 15 and 20 cm mentioned in the original text. For this project, the choice was made over 20 cm in order to facilitate implementation and obtain regular edges.

The pond has a perimeter of 21 m. This first part follows the preparation of the material, the installation of the 40 pickets and their upgrading. Click on the pictures to enlarge them.

1. Prepare equipment

Preparation of the material. From left to right, 20 zobé pickets and 20 ECOPIC plastic pickets are combined to compare the two solutions. A 25 m ECOLAT roll is provided for a pond perimeter of 21 m. The protective felt represents 60 m².

Prepare material · photo 1
Prepare material · photo 1
Prepare material · photo 2
Prepare material · photo 2
Prepare material · photo 3
Prepare material · photo 3

2. EPDM tarpaulin

The site uses 60 m² of EPDM Firestone tarpaulin. The photos show the small footprint of the membrane when it is rolled.

The EPDM tarpaulin · photo 1
The EPDM tarpaulin · photo 1
The EPDM tarpaulin · photo 2
The EPDM tarpaulin · photo 2

3. Laser level

To upgrade the ECOLAT borders, we chose a level equipped with a laser pointer. The price of 25 € quoted in the report corresponds to the period of the construction site.

The laser level · photo 1
The laser level · photo 1
The laser level · photo 2
The laser level · photo 2
The laser level · photo 3
The laser level · photo 3

4. Place Level Benchmarks

For a pond of geometric shape, a string can also be used as a marker. Here, pickets are placed at the four cardinal points and set to the same level.

Place Level Markers · Photo 1
Place Level Markers · Photo 1
Place Level Markers · Photo 2
Place Level Markers · Photo 2
Place level markers · photo 3
Place level markers · photo 3

5. Divide pickets

All pickets are presented and distributed on the periphery of the pond.

Divide pickets · photo 1
Divide pickets · photo 1
Divide pickets · photo 2
Divide pickets · photo 2
Divide pickets · photo 3
Divide pickets · photo 3

6. Throat the pickets partially

The pickets are partially embedded in their final location. The report also reminds, with humour, of the importance of taking a break and getting quenched.

Throttle the pickets partially · photo 1
Throttle the pickets partially · photo 1
Throat the pickets partially · photo 2
Throat the pickets partially · photo 2
Throat the pickets partially · photo 3
Throat the pickets partially · photo 3

7. Adjust heights

Each pole is pushed down to the laser mark. This first upgrade allows you to visualize the differences in height of the ground before laying the ECOLAT borders.

Adjust heights · photo 1
Adjust heights · photo 1
Adjust heights · photo 2
Adjust heights · photo 2
Adjust heights · photo 3
Adjust heights · photo 3

8. Complete the pike draught

All the stakes have to be pushed down. The construction site has 40 stakes and the stony ground makes this stage particularly difficult.

Finish the pike sink · photo 1
Finish the pike sink · photo 1
Finish the pike sink · photo 2
Finish the pike sink · photo 2
Finishing the pike sink · photo 3
Finishing the pike sink · photo 3

The continuation of the project

The six stages of the Serge Pond