We will take care of the pumping unit. The principle is simple: a skimmer (2) in the pond, a mechanical prefiltration of water before it is sent into the lagoon (4 and 5), an automatic adjustment of the water level (6), then the pumping unit with its insulation valves, at the bottom of the plane.
That's what the specifications are for, let's see.

Location of the pumping unit
A gaping hole waits to see the system take place, the electricity for the pump supply is already in place and the main piping also.
Manufacture of zinc casing
Manufacture of dry room for zinc pump, let us not forget that this box will be permanently subjected to moisture as it will be buried.
Inlet of the feed pipe
Drill a hole for the water supply pipe inlet.
The elbow and flange of the circulator
Place the elbow and flange of the circulator through the wall.
The circulator and exits
View of the ferry with the circulator and one of the two exits.
The circulator at a speed
A 1-speed view of the circulator.
The box ready to be laid
That's it, the ferry is ready to be set up next to the filter.