Michael's Lagunage — The Structure
Part 5 · The beginning of the construction project
We have set out to carry out this project. Point 9 of the overall plan is the starting point of the project.

The start of work
This is the construction site that starts, just like on any construction site, it's a mess! A little patience and everything will get back in order.
The sole and the bottom drain
The first operation is to create the bottom sole, which has the outlet of the backwash: the tube and the bottom cap are directly integrated into the concrete (9).
The first layer of concrete
This is the first layer made.
Formwork of the settling chamber
Michael places a frame, of the size of the grid, which will come to this place, notice that the grid occupies virtually the entire surface of the bottom of the lagoon.
The second layer of concrete
A second layer of concrete is cast, this is the area of settling completed.
The connection of the backwash
The backwash pipe (11) is brought to the draining system, notice the valve used, a few seconds opening of the valve will have the effect of desensitizing the settling area of the lagoon.